Jingzhou 1 billion yuan nickel-iron alloy project can be put into operation within the year

Jingzhou 1 billion yuan nickel-iron alloy project can be put into operation within the year As the first one-billion yuan project introduced by Jingzhou City since the strong waist project, the construction progress of the 80,000-ton nickel-iron alloy project of the Yangtze River Nickel Industry has been receiving much attention. Since laying the first pile foundation on April 1 last year, it has passed. Nearly 1 year. How will the project progress, and when will the first nickel-iron alloy produced in Jingzhou be available?

In mid-March, it was the season of sowing hope. The site of the Yangtze River Nickel Project alongside the Yangtze River Avenue was also a fiery construction scene. As a large-scale metallurgical enterprise, the metallurgical furnace and the rotary kiln special plant are the most important projects for the construction of the Yangtze River Nickel project, and it is the large-scale state-owned construction with the qualification of special grade general contracting for this task. Enterprise - China 15 Metallurgical Construction Co., Ltd.

As the May flood season is approaching, the actual time available for construction at present is only about 40 days. In order to quickly seize the construction period, Changjiang Nickel and the 15th Metallurgical Group also adopted a large-scale Corps combat, accumulating more than 500 manpower each day, and strived to completely end the construction of the underground infrastructure before the flood season.

According to briefings, at present, the construction of roads, pile foundations, rain and sewage pipelines, and excavation of deep foundation pits of the Yangtze River Nickel Project has accumulated more than 100 million yuan in total investment, and the next step is in the purchase of reinforced concrete and equipment. The company will also invest more than 100 million yuan to ensure the successful implementation of trial production by the end of August.

In order to fully assist the company in successfully completing the production target within the year, the development zone and the municipal departments have also done a lot of work. At present, the 110 kV transformer substation and plant area water supply and drainage system for the project has been completed, and the Baolian Pier for the transportation of raw materials has been completed. The submerged pile foundation has also been laid, creating conditions for the rapid advancement of the project.

Cordless Circular Saw

The 20V Cordless Circular Saw is Perfect for Cutting Wood, especially on Bevel Cutting and Straight Cutting, compared to the Jig Saw.

The 20V Cordless Wood Working Circular Saw is convenient to use at anywhere, wireless power supply, 4Ah and 2Ah Battery is rechargeable.

4Ah battery can cut around 30m wood.

This Cordless Power Tool is designed friendly, can be used by Left or Right Hand.

It is a cordless wood cutting power tools that users feels much better, compared to jig saw.

The Cordless Wood Working Power Saw with single speed 4000rpm, Laser Function, Bevel Cutting 45°, 55mm cutting depth at 90 Degree, 36 cutting depth at 45 Degree.

The Cordless Circular Saw With a dust blower for max cut -line visibility.

The Cordless Wood Cutting Power Tools with protection button for your safety, soft rubber handle for comfortable use.

Cordless Circular Saw,Portable Circular Saw,Cordless Circular Saw With Battery,Hand Circular Saw

Ningbo Brace Power Tools Co., Ltd , https://www.bracepowertools.com