The estimated investment of the project is 50 million yuan, with a total construction area of ​​5,629 m2, including sub-projects such as fluorite recovery grinding and floating workshop, thick pool, dewatering workshop, drying workshop and storage. At the end of April, the project began to carry out engineering geological exploration and plant site flat foundation. It was originally planned to be completed in early December. However, due to the landslide control of the main plant block and repeated adjustment and modification of the process plan, the design unit submitted the formality in mid-September. Construction drawings, delaying the entire construction period. After that, the company adjusted the trial production time to the 2010 Spring Festival in light of the actual situation.
Since September, the total construction time of the project has only been more than 100 days, and the time is tight and the task is heavy. Since October 1st, the company has organized activities such as “grab the construction period, rushing progress, and fighting for a hundred days to fight hardâ€, mobilizing the resources and strength of the company, the construction unit, the supervision unit, etc., to grasp the fine weather in autumn. At the golden opportunity, make full use of the 100 days before the production, put down a detailed construction plan, and rationally formulate measures to effectively organize the construction. For each sub-project, the construction target responsibility letter was signed with each construction unit, and the inspection and supervision were strengthened. Every 10 days, inspection was held once, and a dispatch meeting was held to inform the construction quality, safety and progress, rewards and punishments. Make arrangements and make requests for progress, quality, and safety.
Hunan Nonferrous Luzhou Fluorine Chemical 100,000 Tons Fluorite Selection Plant Put into Operation
Hunan Nonferrous Metals Holding Group Co., Ltd. 100,000 tons of fluorite plant selection project entered the final stage of hard work, civil construction finishing, equipment installation and commissioning, preparations before production, are in full swing.